Wednesday, April 24, 2024

25 APRIL 2024 HKL

SITE EG MALL 

[10:23, 25/04/2024] +60 16-880 4632: @EG MALL Mr Lo please submit method statement for grouting floor opening..
[10:24, 25/04/2024] EG MALL Mr Lo: Noted
[10:26, 25/04/2024] +60 16-880 4632: @EG MALL Mr Lo please ascertain grouting at L8.Non inspection carry out..do not allow to grout without your supervision..
[10:26, 25/04/2024] EG MALL Mr Lo: Noted

[11:09, 25/04/2024] Kadapi J. PROMES: Boss Lan suru kita buat mock up dengan ducting sebelah unit.
[11:17, 25/04/2024] Kadapi J. PROMES: @Azman HKL @EG MALL ECONMECH Dart @~WY @~sklaw3 @~zee
[11:19, 25/04/2024] EG MALL ECONMECH Dart: Byk piping msuk d sna tu
[11:19, 25/04/2024] EG MALL ECONMECH Dart: Ada refrigerwnt pipe lg
[11:21, 25/04/2024] Kadapi J. PROMES: ๐Ÿ˜… boss lan cakap client complaint sdh
[11:23, 25/04/2024] Kadapi J. PROMES: Bgs ko jumpa Lan ka c tau napa duct kita taru sana. Mcm dia x boleh terima saya punya penerangan๐Ÿ˜…
[11:24, 25/04/2024] Kadapi J. PROMES: #penjelasan
[11:26, 25/04/2024] Azman HKL: @EG MALL ECONMECH Dart ๐Ÿ™๐Ÿ™kau ni harapan. ๐Ÿ™๐Ÿ™๐Ÿ™
[11:26, 25/04/2024] EG MALL ECONMECH Dart: ya sbb tu refpipe xble bend suka2
[11:26, 25/04/2024] EG MALL ECONMECH Dart: ada requirement piping refrigerant klau vrf
[11:27, 25/04/2024] EG MALL ECONMECH Dart: klau chiller pipe ble kta bend suka2
[11:27, 25/04/2024] EG MALL ECONMECH Dart: nt petang sy pg ofis dia
[11:27, 25/04/2024] Kadapi J. PROMES: Ko jumpa dia dart hari ni.
[11:27, 25/04/2024] EG MALL ECONMECH Dart: nt aku update lpas jmpa dia


NSC GROUP 

[08:06, 25/04/2024] Azman HKL: Site progress photo.
25/4/24
20th floor. TA2. Slab formwork and rebar in progress.

[08:10, 25/04/2024] Azman HKL: 20th floor. TA1. Column works in progress.

[08:25, 25/04/2024] Azman HKL: 6th floor. TB6. Slab support, ST2 RC wall, and lift wall in progress.

[08:26, 25/04/2024] Azman HKL: 7th floor. TB5. Slab formwork in progress.

[08:27, 25/04/2024] Azman HKL: 6th floor. TB4. Slab formwork in progress.
[10:48, 25/04/2024] Azman HKL: 20th floor. TA2. Conduit installation in progress.

[10:50, 25/04/2024] Azman HKL: 20th floor. TA2. Plumbing setting out in progress.

[14:09, 25/04/2024] Azman HKL: Mitsubishi PIC lift wall measurement inspection on site.

[14:28, 25/04/2024] Azman HKL: External. MH15. Outlet pipe to MH15 inspection done.

[14:38, 25/04/2024] Azman HKL: Ground floor. Excavation of MH5 in progress.

No comments:

Post a Comment

EGMALL NSC (23 SEPT 2024)

  EGMALL NSC (23 SEPT 2024) [23/9/2024 9:24 AM] EG MALL Mr Lo: @HIDAYA KH office Num ft ya Sini thanks [23/9/2024 9:24 AM] EG MALL Mr Lo: ...