[09:48, 24/04/2024] Azman HKL: 9th floor.  Tower A, Hotel. @Kadapi J. PROMES please if can join us discussion with @~WY @HIDAYA KH office Num . To discuss the pipe routing.πŸ™πŸ‘†. 10am.
[09:49, 24/04/2024] Kadapi J. PROMES: Otw
[09:52, 24/04/2024] Azman HKL: TQ bos.. πŸ™

[11:26, 24/04/2024] Azman HKL: 8th floor. Unit 22. Joint inspection discussion outcome. 
1. Unit 22, Econmech will conceal the slab opening so that Brick can proceed.
2. Other 6 unit, brick work install first. Econmech and King Hong will coring the slab after that.
3. Slab opening arrangement as per site discussion with consultant.
4. Any issue on site, will discuss on site with all parties that involve. Inform Azman for any arrangement. πŸ™
@Kadapi J. PROMES @~WY @HIDAYA KH office Num @~Leppong @~zee

[11:56, 24/04/2024] Azman HKL: 9th floor. M&E coordination on site. Discussions out come.
1. Plumbing will confirm the piping routing on site.
2. Any routing crossing sprinkler pipe will be adjusted on site. 
3. Any obstacle on site will be discussed on site with all parties involve. πŸ™πŸ™
@Kadapi J. PROMES @~WY @HIDAYA KH office Num

[11:56, 24/04/2024] Azman HKL: 9th floor

NSC GROUP

[08:10, 24/04/2024] +60 16-832 2597: @~Roxas Ng (Kai) bagitu tau Kesturi, DCC dan Ming Jie bagi kerjasama dulu
[08:10, 24/04/2024] +60 16-832 2597: To All NSC, rubbish chute is still under maintenance. Pls don’t use it yet ya


[09:25, 24/04/2024] HIDAYA KH office Num: water tank installation at 3rd floor

[09:33, 24/04/2024] Azman HKL: Site photo progress.
24/4/24.
20th floor. TA2. Slab formwork in progress.

[09:33, 24/04/2024] Azman HKL: 20th floor. TA1. Column rebar works in progress.

[09:33, 24/04/2024] Azman HKL: 6th floor. TB6. ST2 wall formwork and Lift wall rebar. Slab support in progress.

[09:33, 24/04/2024] Azman HKL: Ground floor. Cast iron pipe to MH20.

[09:37, 24/04/2024] Azman HKL: 9th floor. @HIDAYA KH office Num @~WY . Itu pipe PVC ada crossing sama itu Sprinkler pipe. Plumbing tolong check ada masalah ka? Kalau ada kita cek dia. πŸ‘†. Saya sini 9th floor skrg.
[09:39, 24/04/2024] HIDAYA KH office Num: iyaa tidak dapat jalan tu pipe kami sana. sprinkler pipe boleh jauh sikit dari riser room area ka?
[09:45, 24/04/2024] Azman HKL: Kalau free skrg, kita cek sini 9th floor. @~WY @HIDAYA KH office Num πŸ™
[09:45, 24/04/2024] HIDAYA KH office Num: okay

[09:56, 24/04/2024] Azman HKL: Jumpa di sini 8th floor dulu ya.

[10:23, 24/04/2024] Azman HKL: Joint inspection dgn NSC


[10:57, 24/04/2024] Azman HKL: 9th floor. Tower A. Joint inspection

[10:58, 24/04/2024] Azman HKL: 8th floor. LPD. @~WY @~Rimon Joseph itu bracket kena reject. Tolong atur dia.

[10:58, 24/04/2024] Azman HKL: Ini juga. Berkarat. Belum siap plug ke lantai.

[14:35, 24/04/2024] Azman HKL: 20th floor. TA2. Slab formwork in progress.

[14:35, 24/04/2024] Azman HKL: 20th floor. TA1. Column work in progress

[14:35, 24/04/2024] Azman HKL: 7th floor. TB5. Slab formwork in progress.

[14:35, 24/04/2024] Azman HKL: 6th floor. TB4. Slab formwork in progress.


[15:21, 24/04/2024] HIDAYA KH office Num: good evening. minta kerjasama semua tolong hati2 dengan pipe kami especially pipe untuk WB di brickwall level 8 ni. banyak suda patah πŸ™πŸΌ
[15:48, 24/04/2024] Azman HKL: Saya inform subcon HKL.
[15:48, 24/04/2024] HIDAYA KH office Num: tq azman