Saturday, March 30, 2024

31 MAC 2024 HKL

 NSC GROUP 

[9:44 am, 31/03/2024] Azman HKL: Site progress photo.
31/3/24
19th floor. TA1. Slab formwork and rebar in progress. 18th floor. TA2. Slab support in progress.

[9:44 am, 31/03/2024] Azman HKL: 5th floor. Slab formwork in progress.

[9:44 am, 31/03/2024] Azman HKL: 7th floor. TB3. Slab formwork in progress.

[4:15 pm, 31/03/2024] Azman HKL: 19th floor..TA1. slab rebar and M&E in progress.




No comments:

Post a Comment

  EGMALL COORDINATION (6 18th floor. Tower B. Installation. ELV, Electrical, ACMV, FF drain pipe services done installation. 18th floor. Tow...