[14:28, 30/03/2024] Azman HKL: 2nd floor. Wiring inspection in progress.
[14:30, 30/03/2024] Azman HKL: 1st floor. Wiring inspection in progress.
[15:26, 30/03/2024] Azman HKL: Ducting fan store temporarily in the ground floor..
NSC GROUP
[8:16 am, 30/03/2024] Azman HKL: Site progress photo.
30/03/2024.
19th floor. TA1. Slab formwork and rebar. 18th TA2. Column rebar, lift wall works, slab scaffolding support.
[8:16 am, 30/03/2024] Azman HKL: 4th floor. TB6. Slab support, ST RC wall rebar, column rebar.
[8:16 am, 30/03/2024] Azman HKL: 7th floor. TB3. Slab formwork.
[8:26 am, 30/03/2024] Azman HKL: Basement. Fire water tank room.@~WY @EG MALL ECONMECH Dart ini duct maw frame? Tolong check MOS? Bata sedang jalan sini ya. Nanti susah kamu pasang.π
[8:49 am, 30/03/2024] Azman HKL: 3rd floor. Water tank room. Water tank no.1 installation in progress. Estimate to complete on Thursday. @~Roxas Ng (Kai) tolong push Subcon kasi siap plinth. π
[3:17 pm, 30/03/2024] Azman HKL: 19th floor. TA1. Slab rebar works in progress..π
[3:18 pm, 30/03/2024] Azman HKL: @~Leppong @~zee πtake note yer. Atur dia. π«°.