[15:38, 25/03/2024] Azman HKL: 4th floor. TB6. Request for inspection at 3.50pm. @Kadapi J. PROMES. Site PIC please stanby on site during inspection. @~Leppong @HIDAYA KH office Num @~WY @~zee .
[16:10, 25/03/2024] Azman HKL: 4th floor. TB6. M&E inspection in progress
NSC GROUP
[08:35, 25/03/2024] Azman HKL: Monday Site Safety Tool Box briefing. 8.30am.
[08:56, 25/03/2024] Azman HKL: 4th floor. TB6. Slab rebar and M&E in progress.
[08:56, 25/03/2024] Azman HKL: 19th floor. TA1. Column rebar and slab form work in progress. 18th floor. TA2. Lift wall rebar in progress.
[10:41, 25/03/2024] Azman HKL: 7th floor. TB3. Slab formwork in progress.
[11:30, 25/03/2024] +60 12-559 6863: For info.
Notice Of Delay from NSC.
1. DCC ✔
2. King Hong ✔
3. Econmech ✔
4. Mitsubishi ✔
5. LSK
6. Gas OiL Equipment (LPG)✔
Reminder kindly submit ASAP to HKL site office.
[16:10, 25/03/2024] Azman HKL: 4th floor. TB6. M&E inspection in progress