Saturday, March 23, 2024

23 MAC 2024 HKL

SITE EG MALL 

[14:40, 23/03/2024] Azman HKL: During slab Coring please be careful of any conduit. Please inform me or electrical NSC to look and get a check.
[14:42, 23/03/2024] Azman HKL: Please report coring progress in group for report progress. TQ

[15:00, 23/03/2024] Azman HKL: 18th floor. TA2. Request for M&E pre-inspection at 3.30pm. @Kadapi J. PROMES . NSC site PIC please stand by on site during inspection. TQ.
[15:32, 23/03/2024] Azman HKL: @~zee kamu punya orang sda start pasang juga ka di 18th. Saya takut lupa kamu lagi. πŸ˜…

[15:53, 23/03/2024] Azman HKL: 18th floor. TA2. Pre-inspection in progress.

[16:00, 23/03/2024] Azman HKL: @~WY Tolong cek itu duct ya. πŸ™
[18:00, 23/03/2024] +60 18-960 2589: masi lagi sini 18th
[19:59, 23/03/2024] Azman HKL: πŸ‘Œ

[20:09, 23/03/2024] Azman HKL: 18th floor. TA2. Inspection done. πŸ‘Œ

 NSC GROUP 

[09:08, 23/03/2024] Azman HKL: Site progress photo.
23/3/24.
18th floor. TA2. Slab formwork, rebar and plumbing pipe in progress.
[09:10, 23/03/2024] Azman HKL: 4th floor. TB6. Slab rebar and M&E works in progress

[09:13, 23/03/2024] Azman HKL: 7th floor. TB3. Slab formwork in progress.
[09:59, 23/03/2024] +60 16-837 8881: Bila cast ya ?
[09:59, 23/03/2024] +60 16-837 8881: Hari ni ?
[10:21, 23/03/2024] Azman HKL: 18th floor, TA2. Cast plan ini hari.
[13:40, 23/03/2024] Azman HKL: 18th floor. TA2. Slab rebar in progress.

[14:43, 23/03/2024] Azman HKL: Zone TB/6: 1F-2F: ST02: Staircase rebar in progress.
[15:56, 23/03/2024] Azman HKL: Electrical riser @~nas4rie tolong kejar ini ya supaya electrical boleh jalan. Banyak point sini. πŸ™πŸ™
[16:13, 23/03/2024] Azman HKL: 8th floor mockup. 4-4 view
[16:13, 23/03/2024] Azman HKL: 2-2 view

[16:13, 23/03/2024] Azman HKL: 1-1 view

[16:13, 23/03/2024] Azman HKL: 4-4 view