[09:00, 06/03/2024] Azman HKL: Morning. As discuss with @~π‘…π’Άπ“Ž π’žπ’½π‘œπ“ƒπ‘” we postpones site walk from the 1st floor to the 2nd floor this coming Friday. So that we can compile all that defect previously to the list reports. @~Johnny @Kadapi J. PROMES @~Jacksonsinti @HIDAYA KH office Num @~Leppong @~WY
[09:01, 06/03/2024] +60 12-559 6863: not 1-2 floor, we go carpark floors starting 3rd on Friday
[09:02, 06/03/2024] +60 16-880 4632: πŸ‘






[09:28, 06/03/2024] +60 16-880 4632: Door frame surround be filled with morter. No gap hollow allow..

[10:10, 06/03/2024] Kadapi J. PROMES: KH, please intall the concealed cold water in proper way. Tq


[10:11, 06/03/2024] Kadapi J. PROMES: This part have to conceal all togerher
[10:11, 06/03/2024] Kadapi J. PROMES: Upvc class 7 cw pipe
[10:13, 06/03/2024] Kadapi J. PROMES: Level 2 public toilet

[10:37, 06/03/2024] +60 12-843 3877: Installation PVC conduit@level 16


[10:40, 06/03/2024] Kadapi J. PROMES: Belum siap tu?
[10:46, 06/03/2024] +60 12-843 3877: Ya
Still in progress ma



[11:38, 06/03/2024] +60 16-880 4632: @~Roxas Ng (Kai) 
Please arrange to make good.

[11:45, 06/03/2024] +60 16-880 4632: Pipe burst.L7
[11:50, 06/03/2024] Azman HKL: Iya. Tecnician akan buat. Mereka ada di atas.


[13:17, 06/03/2024] Azman HKL: 16th floor. TA2. Request for inspection. M&E at 3pm. @Kadapi J. PROMES . NSC PIC please stand by at the site during inspection. @~Leppong @~WY @HIDAYA KH office Num


[14:20, 06/03/2024] +60 16-880 4632: @Kadapi J. PROMES @HIDAYA KH office Num 
Tolong check setting out dimension on site..betul ka .have to forward to ID designer.




[15:12, 06/03/2024] +60 16-880 4632: ST3 floor L2

[15:39, 06/03/2024] Azman HKL: 16th floor. Inspection in progress.

[16:13, 06/03/2024] Azman HKL: 16th floor. TA2. Done M&E inspection. Please proceed. @~nas4rie @Mr. Voo
[16:49, 06/03/2024] Azman HKL: Welcome Mr Thomas, ELV NSC, from LSK System Engineering to Site EGMall Coordination Whatsapp group. πŸ‘πŸ»
[16:51, 06/03/2024] Azman HKL: EGMall George Chia Gas-Oil Equipment LPG NSC
[16:52, 06/03/2024] Azman HKL: Welcome Mr George Chia, LPG NSC, to site EGMall Coordination Whatsapp Group
[16:53, 06/03/2024] Azman HKL: For info. Tomorrow, Site Progress Meeting at Site meeting room at 3pm. Please be inform. TQ. πŸ™


 NSC GROUB

[09:34, 06/03/2024] Azman HKL: Site progress photo. 
6/3/24.
16th floor. TA2. Slab rebar and M&E in progress. 17th floor. TA1. Slab formwork in progress.

[09:34, 06/03/2024] Azman HKL: 4th floor. TB4. Slab rebar and M&E in progress.

[09:35, 06/03/2024] Azman HKL: 3rd floor. TB6. Slab formwork in progress.

[10:47, 06/03/2024] Azman HKL: Ground floor. Escalator assembling/fabricating in progress

[14:37, 06/03/2024] Azman HKL: Lift motor room hook.

[14:37, 06/03/2024] Azman HKL: Ceiling hook

[14:37, 06/03/2024] Azman HKL: Ceiling hook. @~YoonYK πŸ‘†

[15:39, 06/03/2024] Azman HKL: 16th floor. TA2 Inspection in progress.