SITE EG MALL
[08:24, 05/03/2024] Azman HKL: @Kadapi J. PROMES @~Johnny @~Leppong @~WY @Leung KHπ Please join our site walk/inspection at 9am, gather at Ground Floor. π
[08:28, 05/03/2024] +60 16-880 4632: π
[09:07, 05/03/2024] Azman HKL: Kita kumpul sini depan pintu masuk.
[09:17, 05/03/2024] Azman HKL: Defect joint inspection at Groundfloor. Day 2.
[09:54, 05/03/2024] Azman HKL: Smoke Spill Duct has to make a decision. Econmech had discussed with Promes, proposal to Archi to install grill
[10:29, 05/03/2024] Azman HKL: PVC pipe dropper. Econmech will repair as per comment.
[12:15, 05/03/2024] +60 16-880 4632: Client consultent contractor
Nsc.subcon.Site walk and site inspection post concrete and on going works..
[13:43, 05/03/2024] Azman HKL: Ground floor. @~Dart 7090 π²πΎ kasi confirm ini AHU room layout. On site, archi drawing tiada ubah. Tolong confirm sama consultant.
[13:46, 05/03/2024] Azman HKL: Basement. AHU room. @~Dart 7090 π²πΎ ini bilik juga. Archi drawing masih sama.
[13:46, 05/03/2024] +60 19-865 7090: Sdh submit shop dwg
[13:49, 05/03/2024] Azman HKL: Tolong kejar ya. Verbally, Syamsulflan ada komen?
[13:50, 05/03/2024] +60 19-865 7090: Approved with comment
[13:50, 05/03/2024] +60 19-865 7090: Ok man
[13:55, 05/03/2024] Azman HKL: Bos, @~Johnny, @Kadapi J. PROMES later we discuss & check The new AHU room at Basement and Ground floor. So we can proceed if we get approval. π
[13:55, 05/03/2024] +60 16-880 4632: K
[16:41, 05/03/2024] +60 16-880 4632: ST3 L2 Shape out.
NSC GROUP
[09:20, 05/03/2024] Azman HKL: Site joint inspection of defect work at ground floor. Day 2.
[09:29, 05/03/2024] Azman HKL: Site progress photo.
5/3/24.
4th floor. TB4. Slab formwork in progress
[09:29, 05/03/2024] Azman HKL: 2nd floor. TB6. ST2. Retaining wall rebar in progress. Lift wall rebar and formwork in progress
[09:46, 05/03/2024] Azman HKL: Ground floor. Mitsubishi Escalator subcon on site ready to assemble/fabricate for ground floor to 1st floor the Escalator. @~YoonYK please share your daily manpower to this group for my record. Thank you. π
[13:36, 05/03/2024] Azman HKL: 16th floor. TA2 slab rebar and M&E and 17th floor, TA1, slab formwork in progress.
[15:30, 05/03/2024] HIDAYA KH office Num: 7th floor. minta alihkan door frame. kami mau jalan mobile scaffold sini. @Azman HKL @~Roxas Ng (Kai)
[15:31, 05/03/2024] +60 16-832 2597: Ok, saya cari tempat to store ni ya
[15:31, 05/03/2024] HIDAYA KH office Num: okay tqtq ππΌ
[15:53, 05/03/2024] Azman HKL: NSC please submit site work progress by tomorrow. @HIDAYA KH office Num @Recky Econmech @~ShawnChia . π
[15:55, 05/03/2024] Recky Econmech: Ok azmanππ»
[16:39, 05/03/2024] Azman HKL: New Slab Casting Plan
16F - TA2 - 06/3/24
17F - TA2 - 14/3/24
17F - TA1 - 11/3/24
4F - TB4 - 07/3/24 πnew
3F -TB6 - 13/3/24
@~.Fazli @~WY @HIDAYA KH office Num please plan accordingly. π
No comments:
Post a Comment