[08:09, 29/02/2024] Azman HKL: Site progress photo.
29/2/24.
16th floor.TA1. slab rebar in progress.

[08:53, 29/02/2024] Azman HKL: 7th floor. ZP7a. Slab cast.

[11:37, 29/02/2024] Azman HKL: ID meeting at site office meeting room.


[13:35, 29/02/2024] Azman HKL: 16th floor. TA1. Slab rebar and M&E in progress.

[13:35, 29/02/2024] Azman HKL: 4th floor. TB4. Slab formwork in progress.