Wednesday, February 28, 2024

26 FEB 2024 HKL

 NSC GROUP



[09:25, 26/02/2024] Azman HKL: Site progress photo. 
26/4/24.
2nd floor. TB6. Slab formwork, rebar and M&E in progress.

[09:25, 26/02/2024] Azman HKL: 7th floor. Slab formwork, beam rebar, escalator pit in progress.

[09:25, 26/02/2024] Azman HKL: 16th floor. TA1, slab formwork in progress, TA2. Lift wall in progress.

[11:38, 26/02/2024] Azman HKL: Joint inspection and discussion for hotel corridor at 8th floor.

[11:39, 26/02/2024] Azman HKL: 8th floor. Hotel Corridor. As per discussion, we will build a mock up in this area. Trunking, ducting, piping.

[11:39, 26/02/2024] Azman HKL: Service inlet mockup.ducting, trunking

[11:39, 26/02/2024] Azman HKL: 7th floor. Coordination..

[11:39, 26/02/2024] Azman HKL: 4th floor. Sprinkler height discussion.

[14:22, 26/02/2024] Azman HKL: 6th floor, Z7. Slab rebar in progress..

[14:22, 26/02/2024] Azman HKL: 2nd floor, TB6. Slab rebar in progress

[14:25, 26/02/2024] Azman HKL: 7th floor. Zone P7A, slab formwork and beam rebar in progress