[09:57, 25/01/2024] Azman HKL: 6th floor. Lift wall. @~YoonYK @Kadapi J. PROMES request for inspection by today. 2pm.
[09:58, 25/01/2024] +60 19-821 8251: Sorry not able to make it that hour. Can we make it 3pm?
[09:58, 25/01/2024] Azman HKL: Ok. 3pm..
[10:06, 25/01/2024] +60 19-821 8251: Thanks.
[10:48, 25/01/2024] +60 16-880 4632: @~Roxas Ng (Kai) and Arch.m&e team..
As observe on site basement floor to 2nd floor
M&E started to fixing piping and other services related. Please bay in mind and make is Clear all the compartments is with painting finish. You and your team is to plan ahead work smart so that No
Hindering work lift behind. Plastering & painting work yet to complete.to put is right sequence of work. please check and Call for inspection prior proceed further..
[10:48, 25/01/2024] +60 16-832 2597: Noted sir
NSC GROUP
[08:04, 25/01/2024] Mr. Voo: @~Leppong
[08:12, 25/01/2024] +60 17-866 0355: Ok naik sudah ni bos
[09:23, 25/01/2024] Azman HKL: Site progress photo.
25/1/24.
13th floor. TA2. Slab rebar and M&E in progress.
[09:23, 25/01/2024] Azman HKL: 13th floor.. TA2. Column rebar and formwork in progress.
[10:49, 25/01/2024] Azman HKL: @~WY nanti sini minta marking itu AHU plinth.
[10:50, 25/01/2024] +60 14-379 2990: Ok man