[09:05, 17/01/2024] Azman HKL: 12th floor. TA2. Request for M&E slab inspection at 10.30am. @Kadapi J. PROMES . Please NSC PIC stand by on site during inspection.

NSC GROUP

[08:58, 17/01/2024] Azman HKL: Good morning. NSC PIC Kindly post Daily Man power early today before 10am and update Work progress report before 4pm today. TQ. @~.Fazli @HIDAYA KH office Num @~WY @~ShawnChia @Recky Econmech
[09:17, 17/01/2024] +60 12-559 6863: @Dart Econmech any update please ?
[09:18, 17/01/2024] Dart Econmech: preparing drawing and details. will update soon
[09:22, 17/01/2024] Azman HKL: Daily site progress. 
17/01/2024.
12th floor. TA2. Slab rebar and M&E in progress.

[09:22, 17/01/2024] Azman HKL: 12th floor. TA1. Column rebar in progress.

[09:22, 17/01/2024] Azman HKL: Ground floor. TB6. Slab formwork in progress. Basement, Z9, retaining wall rebar in progress.

[09:22, 17/01/2024] Azman HKL: 4th floor. Ramp 6. Beam rebar in progress. 5th floor. Z7. Slab rebar in progress. 6th floor. Z6. Slab rebar in progress.

[09:25, 17/01/2024] +60 12-559 6863: Please also provide sections or front elevation
[09:31, 17/01/2024] +60 19-821 8251: @Azman HKL @~π‘…π’Άπ“Ž π’žπ’½π‘œπ“ƒπ‘” Good morning, seek approval to deliver escalators to level 1 on 18th of january 2024. As all the escalators will need hoist up from 1st floor to each desicated floor during installation.

[11:19, 17/01/2024] Azman HKL: 12th floor. TA2. M&E inspection done. @Mr. Voo @~nas4rie please proceed. πŸ‘Œ
[11:22, 17/01/2024] Azman HKL: Noted. Please meet up this afternoon. 2pm to discuss your method. @Jimmy HKL please joint us. We seek your advise. πŸ™

[13:46, 17/01/2024] Mr. Voo: Ni ok kah ? @HIDAYA KH office Num
[13:48, 17/01/2024] HIDAYA KH office Num: belum. 4" tu mau welding lagi
[13:52, 17/01/2024] Mr. Voo: Bah sila atur , formwork sampai sana sdh
[13:55, 17/01/2024] HIDAYA KH office Num: ya boss
[14:18, 17/01/2024] +60 19-821 8251: As per our discussion just now, we are going to deliver 14 nos. Escalator to site tomorrow morning which gonna last for 3 days, day and night. Escalators going to store at level 1 and ground floor and each escalator equipment weight around 5 to 6 ton. Thanks.
[14:51, 17/01/2024] HIDAYA KH office Num: done boss
[14:52, 17/01/2024] Mr. Voo: Thxs 

[15:44, 17/01/2024] Azman HKL: 6th floor. Z6. M&E inspection done. Please proceed. @Mr. Voo @~nas4rie