SITE EG MALL
[09:50, 06/02/2024] Azman HKL: AHU room. @~WY please catchup your AHU plinth marking on site, so we can call Subcon to build it. @EG MALL ECONMECH Dart when will AHU arrival. Got a date so we can plan?
[09:51, 06/02/2024] EG MALL ECONMECH Dart: Est on nextmonth
[09:51, 06/02/2024] EG MALL ECONMECH Dart: For basement and grd floor
[09:51, 06/02/2024] EG MALL ECONMECH Dart: Including fan also
[09:52, 06/02/2024] Azman HKL: Need to catchup. Plinth not ready. Some changes at ground floor please confirm ASAP.
[09:52, 06/02/2024] EG MALL ECONMECH Dart: Will giv u the est date.
[09:53, 06/02/2024] Azman HKL: @EG MALL ECONMECH Dart please chase/remind me to build that plinth. It takes time.
[09:54, 06/02/2024] EG MALL ECONMECH Dart: Ok man. ππ»ππ»
[10:09, 06/02/2024] EG MALL ECONMECH Dart: ACMV Equipment Delivery
1. Ventilation fan - Batch 1 - All basement including electrical room - 28th feb 2024
2. Ahu and Fcu - Batch 1 - Basement and Grd - 15th March 2024
NSC GROUP
[09:19, 06/02/2024] HIDAYA KH office Num: morning. @Azman HKL kami mau minta clear orang tinggal dalam ni. kami mau jalan pipe sini. toilet ground floor. ππΌ
[09:37, 06/02/2024] Azman HKL: Coldwater di wall brick ka?
[09:38, 06/02/2024] HIDAYA KH office Num: sw pipe
[09:40, 06/02/2024] Azman HKL: 1st floor. AHU room. @~WY bata sudah naik. Nanti pg cek dia.
[10:00, 06/02/2024] Azman HKL: @~WY mana bilik AHU yang sda ready untuk plinth. Bagi saya di drawing. Maw kejar subcon pasang plinth.
[10:04, 06/02/2024] Azman HKL: 1st floor. Ini semua ready sda ka?
[11:22, 06/02/2024] Azman HKL: Site progress photo. 6/2/24. 14th floor. TA2. Slab cast.
[11:22, 06/02/2024] Azman HKL: 15th floor. TA1. Slab formwork and beam rebar in progress.
[11:22, 06/02/2024] Azman HKL: 1st floor. TB6. Slab formwork, slab/beam rebar and M&E in progress.
[11:22, 06/02/2024] Azman HKL: Ground floor. Z8. Slab formwork and beam rebar in progress.
[11:24, 06/02/2024] Azman HKL: TB6 & Z8 casting plan on 8/2/24. Please take note..@~WY @HIDAYA KH office Num @~Leppong
[14:40, 06/02/2024] Azman HKL: Ini Ground floor, Z8 new casting plan tomorrow. 7/2/2024. @HIDAYA KH office Num @~Leppong @~WY . π
[15:02, 06/02/2024] Azman HKL: 7th floor. TA hotel. Wall brick in progress. @~Leppong @~WY @HIDAYA KH office Num please be aware. Potong bata sebelum plaster work.
[15:02, 06/02/2024] Azman HKL: Ok noted. Nanti saya inform subcon.