Friday, December 29, 2023

30 DEC 2023 HKL

SITE EG MALL

[10:24, 30/12/2023] Azman HKL: 6th floor. TB5. Request for inspection M&E services at 2pm.

[10:25, 30/12/2023] Azman HKL: 10th floor. TA2. M&E services are in progress.

[10:32, 30/12/2023] Azman HKL: @Dart Econmech @~Walker Yapi please chase your subcon to complete their electrical conduit. πŸ™πŸ™
[10:32, 30/12/2023] Dart Econmech: Ya sdg atur man. Nt team aku turun bt. Dorg d L10 kjp lg turun


NSC GROUP 

[08:55, 30/12/2023] Azman HKL: Site progress photo.
30/12/2023.
10th floor. TA2. Slab rebar and M&E in progress.


[08:55, 30/12/2023] Azman HKL: 11th floor. TA1. Slab formwork in progress. Column rebar in progress.

[08:55, 30/12/2023] Azman HKL: 6th floor. TB5. Slab rebar and M&E in progress.

[08:55, 30/12/2023] Azman HKL: 4th floor. Z7. Slab casted. 6th floor. Z6. Slab rebar in progress.
[08:57, 30/12/2023] +60 12-559 6863: New Casting Plan
6F - Z6 - 23/12/23 TBU
4F - Z7 - 29/12/23✅
6F - TB5 - 30/13/2023 πŸ‘ˆ
10F - TA/1 - 27/12/23✅
10F - TA/2 - 30/12/23πŸ‘ˆ
[08:58, 30/12/2023] +60 12-559 6863: Dear all, kindly work together to achieve these 2 casting today to close our 2023 with good omens ya, thank you
[08:58, 30/12/2023] +60 12-559 6863: and start the 2024 with greater progress and achievements for allπŸ™πŸ™πŸ™

[10:15, 30/12/2023] Azman HKL: Morning. @~Walker Yapi @~Rimon Joseph fire and Acmv conduit. Tolong push kamu punya subcon. Ini belum jalan..

[10:39, 30/12/2023] +60 16-832 2597: @~Walker Yapi kindly update us next time for future erection of scaffolding.. was querying around to found out.. so can avoid future issues from occurring Tq
[10:45, 30/12/2023] Azman HKL: @~Walker Yapi @~Rimon Joseph tolong ya atur dan inform HKL atau SSS dulu..
[11:43, 30/12/2023] Lo. W. H (HKL-Site Engineer): @HIDAYA KH office Num any flow trap photo work done for the casting tonight
[11:47, 30/12/2023] HIDAYA KH office Num: none

[14:11, 30/12/2023] Azman HKL: 10th floor. TA2. Slab rebar and M&E in progress.

[14:11, 30/12/2023] Azman HKL: 11th floor. TA2. Slab formwork in progress.

[14:11, 30/12/2023] Azman HKL: 6th floor. Z6. Slab rebar in progress.

[14:29, 30/12/2023] Azman HKL: 6th floor. TB5. M&E inspection in progress.
[14:37, 30/12/2023] Azman HKL: Done inspection. @~nas4rie please proceed πŸ‘Œ

[14:47, 30/12/2023] Azman HKL: 10th floor. TA2. M&E services pre-inspection in progress.

[15:56, 30/12/2023] Azman HKL: 10th floor. TA2. Fire and Acmv services inspection in progress.

[16:00, 30/12/2023] Azman HKL: M&E inspection done. @~nas4rie please proceed.. πŸ‘ŒπŸ’ͺπŸ‘πŸ». TQ all.