[08:50, 03/01/2024] HIDAYA KH office Num: morning. @Azman HKL minta tolong tolak tepi besi & kayu jadi kami boleh jalan pipe sleeves pagi ni
[08:56, 03/01/2024] Azman HKL: Ada sda marking drop? Yang di bulat ituka? Berapa yang boleh buat sda? Buat dulu tempat yang sda clear. Ini nanti saya minta subcon mereka tolong pindah. Macam sedang clearing juga tu di atas. @PHKL EG Mall Nasri tolong dulu yeh. ππ
[09:02, 03/01/2024] HIDAYA KH office Num: ada suda marking. sekarang mcm baru dapat buat 2 ja.
[09:41, 03/01/2024] Azman HKL: Ok. Saya ingat mereka sedang buat clearing itu ini hari.
[09:47, 03/01/2024] Azman HKL: Site photo progress.
3/1/24.11th floor. TA1. Slab formwork/ clearing and plumbing pipe sleeve in progress.
[09:47, 03/01/2024] Azman HKL: 10th floor. TA2. Column rebar in progress.
[09:47, 03/01/2024] Azman HKL: 6th floor. TB5.
[09:47, 03/01/2024] Azman HKL: 4th floor. Z7. Column rebar and formwork in progress. 6th floor. Z6. Slab rebar and M&E in progress.
[09:47, 03/01/2024] Azman HKL: 10th floor. TA2. Column rebar and lift wall rebar in progress.
[10:10, 03/01/2024] Azman HKL: ST5 . 8th floor to 9th floor.
[11:38, 03/01/2024] Azman HKL: DCC genset supplier and lifting specialist on site.
[12:11, 03/01/2024] Azman HKL: Also they request to relocate all this steel bar for their mobile crane Outrigger. @~nas4rie π
[12:14, 03/01/2024] Azman HKL: Bos @~π
πΆπ ππ½πππ @Jimmy HKL . Today. The new mobile crane specialist, for DCC genset supplier requested to excavate this area for their mobile crane outriger spaces. I believe, this is the border of our neighbour land