25 DEC 2023 HKL

NSC GROUP 

[08:14, 25/12/2023] Azman HKL: Site photo progress. 
25/12/2023.
10th floor. TA1. Slab formwork in progress. 9th floor. TA2. Lift wall, column rebar and scaffolding support in progress.

[08:14, 25/12/2023] Azman HKL: 6th floor. TB5. Slab formwork and scaffolding in progress.

[08:14, 25/12/2023] Azman HKL: 6th floor. TB3, column rebar in progress.

[08:14, 25/12/2023] Azman HKL: 4th floor. Z7. Slab formwork in progress. 6th floor. Z6. Slab formwork in progress.

[08:15, 25/12/2023] Azman HKL: Basement. Z9. Lift wall formwork in progress.
[08:26, 25/12/2023] HIDAYA KH office Num: morning. minta tolong clear 10th floor TA1. kami mau install pipe sleeves pagi ni tidak dapat jalan lagi. @Azman HKL 🙏🏼
[08:31, 25/12/2023] Azman HKL: Iya. Saya chase dia org. @~nas4rie tolong push GnB juga ya. 🙏

[13:56, 25/12/2023] Azman HKL: 10th floor. TA1. Slab rebar and plumbing pipe sleeve in progress.