[09:05, 24/12/2023] Azman HKL: Site photo progress.
24/12/2023.
10th floor. TA1. Slab formwork in progress. 9th floor. TA2. Lift wall and column rebar in progress
[09:05, 24/12/2023] Azman HKL: 7th floor. Z4. Slab cast.
[09:05, 24/12/2023] Azman HKL: 4th floor. Z7. Slab formwork in progress.
[09:05, 24/12/2023] Azman HKL: 6th floor. TB5. Slab formwork and scaffolding in progress.
[10:23, 24/12/2023] Azman HKL: 10h floor, TA1. slab marking done by Surveyor.. @Leung KH🍀 @Dart Econmech