Friday, December 22, 2023

23 DEC 2023 HKL

SITE EG MALL 

[14:34, 23/12/2023] Azman HKL: 7th floor. Z4. Request for inspection M&E services at 3pm. @Kadapi J. PROMES. All NSC incharges please stand by RFI form and latest drawing before inspection. TQ.
[14:58, 23/12/2023] Kadapi J. PROMES: 👌

NSC GROUP


[09:30, 23/12/2023] Azman HKL: Good morning. 
Site progress photo. 
23/12/2023.
7th floor. Z4. Slab rebar and M&E in progress.

[09:30, 23/12/2023] Azman HKL: 10th floor. TA1. Slab formwork in progress. 9th floor. TA2. Scaffolding work and column rebar in progress.

[09:30, 23/12/2023] Azman HKL: 6th floor. TB3. Slab cast.

[09:30, 23/12/2023] Azman HKL: 3rd floor. Z7.  Ramp5 cast. 4th floor. Slab formwork in progress.

[15:10, 23/12/2023] Azman HKL: 7th floor. Z4. M&E services inspection in progress.

[15:35, 23/12/2023] Azman HKL: Fire services inspection inprogress..

[15:38, 23/12/2023] Azman HKL: Plumbing services inspection in progress.
[16:09, 23/12/2023] Azman HKL: New Casting Plan
6F - Z6 - 23/12/23 TBU
9F - TA/2 -21/12/23✅
6F - TB3 - 21/12/23✅
4F - Z7 - 21/12/23 TBU
7F - Z4 - 23/12/23 today
Ramp4 - 22/12/23✅
10F - TA/1 - 26/12/23
10F - TA/2 - 31/12/23

👈=Changes
Please make plan for working on Holiday. We will update any changes during the holiday.

[16:10, 23/12/2023] Azman HKL: 10th floor. TA1 lab formwork in progress and 9th floor TA2. Column rebar and scaffolding in progress.