Sunday, November 19, 2023

20 NOV 23 HKL

SITE GROUP
EG MALL Azman: 2nd floor. TB4. Request for inspection today at 3pm. @Kadapi J. PROMES . NSC please stand by and prepare with RFI form and drawing.

NSC GROUP
+60 10-941 8970: @EG MALL Azman plss double check for lift door opening at zone TA1 7F-8F thank you 🫡
EG MALL Azman: @~nas4rie already arrange 3pm Mitsubishi will come to. 👆@~YoonYK confirm 3pm can come kan?
 +60 19-821 8251: Yes. Button?
+60 12-843 3877: Installation pvc conduit for ELE/ELV @level 4 in progress
EG MALL Azman: Work in progress.👆
 EG MALL Azman: Site progress photo.
20/11/2023.
2nd floor. TB4. Slab rebar and M&E in progress.
 EG MALL Azman: 5th floor. Z6. Slab rebar and M&E in progress.
 EG MALL Azman: 4th floor. TB5. Slab formwork in progress.
 EG MALL Azman: 4th floor. TB3. Slab formwork in progress.
EG MALL Azman: 2nd floor. Z7 ramp slab formwork and column rebar in progress.
 EG MALL Azman: 7th floor. TA1. Lift wall rebar in progress.
 EG MALL Azman: Basement. Z9. Lift pit BL1. Rebar and formwork in progress.
 EG MALL Azman: ST7. SPD. @~Walker Yapi @Dart Econmech please comply consultant comment ASAP before boxes closing.
EG MALL Azman: Basement lift pit inspection by consultant and Mitsubishi done. 👌
 EG MALL Azman: 2nd floor. TB4. M&E services inspections are in progress.
EG MALL Azman: Electrical inspection.
EG MALL Azman: 2nd floor. TB4. M&E inspection done. @Mr. Voo @~nas4rie please proceed 👌





























 