Monday, October 23, 2023

24 OCT 23 HKL

SITE GROUP
EG MALL Azman: Request for inspection. 2nd floor. TB3. At 3pm @Kadapi J. PROMES NSC please be ready at site.
 EG MALL Azman: Hujan..😭
Kadapi J. PROMES: 😅



NSC GROUP

EG MALL Azman: 2nd floor. TB3. Slab rebar and M&E services in progress.
EG MALL Azman: 2nd floor. TB5. Slab rebar in progress.
] EG MALL Azman: 1st floor. TB4. Slab formwork in progress.
EG MALL Azman: 1st floor. Z8. Slab/ beam formwork in progress.
 EG MALL Azman: Basement. Z9. Earth work & slab foundation in progress.
 EG MALL Azman: Basement. Earthwork in progress.
EG MALL Azman: Ground floor. TB4a. Beam cast. Slab backfill in progress.

 EG MALL Azman: Daily man power. Tolong update ni hari. TQ.


 +60 12-843 3877: Installation trunking&wiring works@level 3
EG MALL Azman: @~.Fazli 2nd floor. TB3. Siap suda itu lantai?
 +60 12-843 3877: Conduit kah?
EG MALL Azman: New Casting plan

6F - TB2 -  ✔️
6F - TA1 - ✔️
3F - TA2 - ✔️
GF - TB4/a -25/10
2F - TB3 - 24/10
2F - TB5 - 26/10
1F - Z8- 28/10

Please coordinate material, man power and drawing onsite. Date may be changed due to site condition.
 EG MALL Azman: Iya.
+60 12-843 3877: 🤞🏻ok siap sudah.

EG MALL Azman: Tolong gambar itu hacking sana SESB room.
HIDAYA KH office Num: 2nd floor
 EG MALL Azman: 2nd floor. TB3. M&E services inspection done. @~Nasri @Mr. Voo please proceed. 👌

EG MALL Azman: Site walk with konsultan and NSC.

































 