18 OCT 23 HKL

SITE GROUP
EG MALL Azman: 6th floor. TA1. Request for Inspection M&E services at slab, 9.30am. @Kadapi J. PROMES

NSC GROUP

 EG MALL Azman: Site progress photo.
18/10/23.
Ground floor. Z8. Slab & beam rebar in progress.
EG MALL Azman: 4th floor. TA2. Slab formwork in progress.
EG MALL Azman: 6th floor. TA1. Slab rebar and M&E ready for inspection.
 EG MALL Azman: Basement. Z9. Earthwork in progress
 EG MALL Azman: Basement. Earthwork in progress
 EG MALL Azman: 2nd floor. TB3. Slab formwork in progress.
EG MALL Azman: 2nd floor. TB5. Slab formwork and column rebar in progress.
 EG MALL Azman: Conduit installation rejected. Please make it good. Conduit below the bottom rebar. 👆@~Walker Yapi
 +60 14-379 2990: Noted.
 +60 19-809 6068: *done
EG MALL Azman: 6th floor. TA1. M&E inspection done. @Mr. Voo @~Nasri please proceed.






















 