EG MALL Azman: @~Walker Yapi @~Rimon Joseph tolong jumpa sama Joseph dgn Kai. 👆ini macam mana hari tu kamu bincang. 🙏cari cara macam mana maw settle dalam site.
Raymond Chong. Y. F (HKL P. Manager): @EG MALL Azman apa isu dia?
EG MALL Azman: Pressurize ducting..
Raymond Chong. Y. F (HKL P. Manager): Ok
EG MALL Azman: Site photo progress.
3/9/23.
Basement. 5b. Retaining wall formwork closure in progress.
EG MALL Azman: 5th floor. TB2. Slab rebar and M&E services in progress.
EG MALL Azman: 1st floor. TB5. Slab formwork in progress
EG MALL Azman: 1s floor. TB3. Slab formwork in progress
EG MALL Azman: 6th floor. TA1. Slab formwork in progress
EG MALL Azman: @Leung KH🍀 @HIDAYA KH office Num kasi confirm pipe sleeve cepat. 👆.
HIDAYA KH office Num: Pipe sleeves tunggu beam nanti.
EG MALL Azman: Ok noted. 👌boleh tutup saja itu wall sekarang kan. Itu beam sekali sama slab nanti.