EG MALL Azman: Site photo progress
2/10/23.
6th floor. TA1. Slab formwork and scaffolding support in progress.
EG MALL Azman: 1st floor. TB3. Slab formwork and scaffolding support in progress.
EG MALL Azman: 1st floor. TB5/TB4. Slab formwork and scaffolding support in progress. Column rebar in progress.
EG MALL Azman: 2nd floor. TA2. Slab cast.
EG MALL Azman: Ground floor. TB2. Slab hack for escalator opening.
EG MALL Azman: 5th floor. TB2. Slab formwork and rebar in progress.
EG MALL Azman: Basement. 4b. Column & retaining wall rebar in progress.
EG MALL Azman: Basement. 5b. Dismantling retaining wall formwork in progress
EG MALL Azman: @~Walker Yapi @~Rimon Joseph daily man power..
+60 12-843 3877: Level 4.wiring in progress
EG MALL Azman: 👆🙏🙏🙏
+60 14-379 2990: Hari ini.. 🙏🏻
EG MALL Azman: Ground floor. Escalator joint inspection opening with Mitsubishi and consultant.