Sunday, September 24, 2023

25 SEP 23 HKL

SITE GROUP

EG MALL Azman: Good morning.
Site progress photo.
25/09/23.
Ground floor. TB5. Slab cast.
EG MALL Azman: 5th floor. TA1. Slab rebar in progress.
EG MALL Azman: 4th floor. TB2. Slab rebar in progress
EG MALL Azman: 4th floor. Z6. Parapet wall rebar and lift formwork.

 EG MALL Azman: Basement. Z5b. Plinth formwork &  retaining wall rebar in progress.
 EG MALL Azman: 2nd floor. TA2. Slab formwork in progress. Ground floor, slab cast.
 EG MALL Azman: Ground floor. TB3/TB4. Column formwork.
 EG MALL Azman: 4th floor. TB2. RFI slab M&E services. 3pm. @Kadapi J. PROMES . NSC involved please standby on site. TQ.
EG MALL Azman: M&E services inspection in progress.


NSC GROUP
 EG MALL Azman: 5th floor. TA1. Conduit installation in progress.
 EG MALL Azman: 4th floor. TB2. Conduit installation in progress.
EG MALL Azman: Please be informed. This week's Client Site Meeting is on Wednesday. 3.00pm.
 EG MALL Azman: @~Walker Yapi @~Rimon Joseph daily man power.. 20hb- 25hb.. bagi saya.
+60 17-866 0355: Azman  tolong bagi tau GNB  punya orang' jangan ampai tu mesin atas pipe
EG MALL Azman: Ok..
 EG MALL Azman: @~Walker Yapi @HIDAYA KH office Num please double check and confirm the water tank plinth dimension and height.👆
 EG MALL Azman: 4th floor. TB2. M&E services inspection in progress.
 EG MALL Azman: Done inspection. @Mr. Voo @~Nasri please proceed..👌



























 