EG MALL Azman: Morning.
Site progress photo.
20/09/23.
Basement. 5b. Slab cast.
EG MALL Azman: Basement earthwork in progress.
EG MALL Azman: Basement earthwork in progress.
EG MALL Azman: Ground floor. TB5. Beam and slab rebar in progress.
EG MALL Azman: 1st floor. TA2. Column rebar in progress.
EG MALL Azman: 4th floor. Lift formwork and parapet rebar.
EG MALL Azman: 5th floor. TA1. Slab formwork in progress
EG MALL Azman: 7th floor. Z4. Slab formwork
EG MALL Azman: Ground floor. TB3/TB4. Column rebar in progress.
EG MALL Azman: Ground floor. Slab formwork in progress. Basement. 4B. Slab foundation rebar in progress.
EG MALL Azman: @Dart Econmech @~Walker Yapi please push your sprinkler subcon start work by this week as you mention to me. Your materials are ready on site. 🙏🙏
Dart Econmech: Mobilize manpower this week
EG MALL Azman: 😘😘😘
Dart Econmech: We will start cut, fabricate pipe, threading. We start ar L3 first
Dart Econmech: Then hope yr spk riser masonry works frm grd to L6 can be done also 🙏🏿
Dart Econmech: So we can start our main pipe 🙏🏿
EG MALL Azman: Noted. Any site problem informs us and we will look at it so that work can proceed.
EG MALL Azman: @~Walker Yapi tolong atur dia cepat.. 👆