Azman HKL: Site progress picture.
10/8/23.
3rd floor. Zone 6. Slab rebar & M&E in progress.
Azman HKL: 1st floor. TB2. Slab formwork in progress.
Azman HKL: 5th floor. Zone 4. Column rebar in progress.
Azman HKL: Ground floor. TB3. Slab formwork in progress.
Azman HKL: 6th floor. 5b. Slab formwork in progress.
Azman HKL: 6th floor. 5a. Slab rebar in progress.
Azman HKL: 3rd floor. TA1. Slab formwork in progress.
Azman HKL: Setting out the genset silencer at the genset room in progress.
Azman HKL: Brick wall setting out inspection with archi consultant.
+60 17-866 0355: 2 point lampu sudah rosak tidak dapat repair. Terpaksa pasang guna G.I saja.
+60 17-866 0355: 4th floor, zone 5a.
Azman HKL: 😱 okay. Nanti kita discuss untuk repair dia. Kita bincang sama consultant on site nanti. 👌
Azman HKL: 3rd floor. Zone 6. Slab & staircase rebar in progress.
Azman HKL: 1st floor. TB2. Formwork in progress. Basement 8a. Staircase rebar in progress.
Azman HKL: Genset silencer opening setting & installation.