Thursday, July 27, 2023

28 JULY 23 HKL

 NSC GROUP

Azman HKL: Good morning. 
Site progress picture.
28/07/2023.
Basement. Slab foundation cast.
Azman HKL: 2nd floor. TA1. Slab rebar and M&E in progress.
Azman HKL: 5th floor. Zone 4. Slab formwork in progress.
Azman HKL: 5th floor. Zone 5a. Cast.
Azman HKL: 5th floor. 5b. Slab formwork in progress.
Azman HKL: 5th floor. TB1. Slab formwork in progress.
Azman HKL: Basement. 8a/8b. Retaining wall and column rebar in progress
 Azman HKL: 2nd floor. Zone 6. Column, parapet wall and lift wall in progress.
















No comments:

Post a Comment

  EGMALL COORDINATION (6 18th floor. Tower B. Installation. ELV, Electrical, ACMV, FF drain pipe services done installation. 18th floor. Tow...