Thursday, July 27, 2023

27 JULY 23 HKL


NSC GROUP

Azman HKL: Good morning. 
Site progress picture.
27/07/2023.
5th floor. 5a slab cast.
Azman HKL: 5th floor. Zone 4. Slab formwork and column rebar in progress.
Azman HKL: 5th floor. TB1. Slab formwork in progress.
Azman HKL: Basement. Slab foundation rebar in progress.
 Azman HKL: 2nd floor. Slab rebar in progress.
 Azman HKL: 2nd floor. Zone 6. Lift wall formwork, parapet wall and column in progress.
Azman HKL: Basement. Zone 8a/8b. Column rebar, retaining wall formwork in progress.
Azman HKL: Basement, earthwork in progress
Azman HKL: Basement, earthwork in progress

 Azman HKL: @Dart Econmech please confirm your AHU plint dimension and mark it onsite top bar, so CnS can cast together.. 🙏🙏🙏
Dart Econmech: Ahu belum design bos
Dart Econmech: Cmna mau marking 😅
Dart Econmech: We still havent received any new dwg from consultant for acmv & ff based on new layout. Wht we can do now is holding yr brick wall for ahu equipment enter the room
Azman HKL: @Raymond Chong. Y. F (HKL P. Manager) please advise.. itu AHU plinth maw hold atau sekali cast. 2nd floor, TA1.
 Raymond Chong. Y. F (HKL P. Manager): Hold klao drawing belum confirm
Azman HKL: Ok bos. Noted. 👌

Azman HKL: Siapa punya kereta, tolong alih ya..
























 