Wednesday, May 24, 2023

25 MAY 23 HKL

 

SITE GROUP

Azman HKL: 2nd floor. Zone 4. Column rebar and scaffolding in progress.
Azman HKL: 3rd floor. Zone 5. Slab formwork in progress.
Azman HKL: 6th floor.
Azman HKL: 2nd floor. Zone TA1. Slab rebar and M&E in progress.
 Azman HKL: Ground floor. Zone 6. Slab formwork and bean rebar In progress.
Azman HKL: Ground floor. Zone TB1 slab cast.
Azman HKL: Basement. Zone 3A. Slab foundation rebar in progress.
 Azman HKL: Ground floor. TB2. Slab formwork inprogress.
 Azman HKL: Basement. Zone TB3 cast. TB4 earth in progress.
 Azman HKL: @~Walker Yapi cek kamu punya top ducting high. Ini kami cek 2800mm dr finish floor. Ada 400mm lagi dari ceiling level.
 Kadapi J. PROMES: As perdiscussed in coordination meeting few days a go. The MSCL pipe should crossing ducting GL 9-10 so that the servicess will not clash with others. But this way it may clashed with big ducting. Please coordinate properly Econmech & KH as i advice early b 4 u starting ur underneath installation few month a go. Tq
Kadapi J. PROMES: U r addvised  to follow coordination drawing given by the maincon coordinator. Tq