 Kadapi J. PROMES: Dear all NSC's, RFI running number is very important. If got issue on the works related easy for us to find out references.
Kadapi J. PROMES: And easy to arrange rfi also with running numbers. Tq
Azman HKL: Yes noted. All Rfi got running number recorded also in form before filing. Due to that time of submission and inspection issue, some of it left blank before inspection.
Azman HKL: After inspection I put in the ref number.
Azman HKL: So NSC, please submit your RFI early to me, so that I can arrange it properly. Also make sure you got your own list of forms submitted for reference.
 Kadapi J. PROMES: Please put washer and nut for better grap. Tq
 Kadapi J. PROMES: Dear NSC's, permenant installation should have washer and nut for better graps for any hanging installation that use thread rod underneath slab nor beams. Tq
 Azman HKL: Site progress picture. 19/05/2023.
6th floor.
 Azman HKL: 2nd floor. Slab formwork in progress.
 Azman HKL: Basement. 7b. Scaffolding support in progress. 7C, foundation rebar in progress.
Azman HKL: Ground floor. zone 5. Slab formwork in progress.
 Azman HKL: Ground floor. TA1. Slab formwork in progress.
 Azman HKL: 2nd floor. 4. Scaffolding support in progress.
 Azman HKL: 3rd floor. Zone 5 slab formwork in progress..


NSC GROUP

Azman HKL: Ground floor. TA1. Conduit marking at slab in pogress.
Azman HKL: Basement. The sanitary pipe runs at a high level in progress.
Azman HKL: Ground floor. TA1. Pipe sleeve and box opening for M&E services.





Latest revised archi drawing for escalator pit

Lo. W. H (HKL-Site Engineer): Dear valued NSC, this is 5th & 6th floor flat slab

Lo. W. H (HKL-Site Engineer): na tengok kamu kenyang kah x ....😆































 

No comments:

Post a Comment

EGMALL NSC (23 SEPT 2024)

  EGMALL NSC (23 SEPT 2024) [23/9/2024 9:24 AM] EG MALL Mr Lo: @HIDAYA KH office Num ft ya Sini thanks [23/9/2024 9:24 AM] EG MALL Mr Lo: ...