SITE GROUP
Azman HKL: Good morning.
Site progress pic.
15/05/2023.
6th floor.
Azman HKL: 2nd floor. Zone 4. Slab rebar and beam rebar in progress.
Azman HKL: Ground floor. Zone TA1. Slab formwork and lift formwork in progress
Azman HKL: 2nd floor. Zone TB1. Slab formwork in progress.
Azman HKL: Basement zone 7B. 1st floor scaffolding beam support in progress
Azman HKL: @KH Karen @Edwin Chen 013 @Leung KH🍀 for 3rd floor. We will use the floor flat slab. There is a 3mx3m Hammerhead slab at the column. Please study and submit as soon as possibble.
Edwin Chen 013: Confirm Using Flat slab at this area?
Azman HKL: Yes..
NSC GROUP
Azman HKL: Casting plan by today. @~ShawnChia @Leung KH🍀 @~Walker Yapi . Please plan to make it done by today. More man power if needed. 🙏🙏🙏.
+60 16-837 8881: Ya man , tapi saya minta balik masa MnE ya 🙏🏻
Pasal kemarin kami belum boleh masuk , tapi hari ni mahu cast ......
Azman HKL: Subcon added more man power to complete slab rebar.
KH Karen: @Azman HKL ini latest?
Azman HKL: Ni saja. Kalau ada baru sy share.
Lo. W. H (HKL-Site Engineer): Dear all, is the archi cad file that i share here, few days ago, differ too much from what you adopt in your shop drawing ?
Lo. W. H (HKL-Site Engineer): Dear valued NSC, 2nd floor flat slab layout with detail