Wednesday, May 10, 2023

11 MAY 23 HKL

SITE GROUP

Raymond Chong. Y. F (HKL P. Manager): ๐Ÿ‘† @Azman HKL



NSC GROUP
 +60 17-866 0355: 2nd floor
 Azman HKL: 11/05/2023.
Site progress pic. 6th floor.
 Azman HKL: 2nd floor. Zone 5. Slab & beam rebar in progress.
 Azman HKL: 2nd floor. Zone 4. Slab beam and rebar in progress.
Azman HKL: 2nd floor, TB1, beam and slab formwork in progress.
 Azman HKL: Basement. Zone TA1. Slab & lift formwork in progress.
Azman HKL: Basement zone 7B. Column rebar in progress.
Azman HKL: Basement zone 5a. Retaining wall and lift formwork in progress.



 Azman HKL: For inform. Subcon target tomorrow ready for slab bottom bar so M&E can continue installation. @~ShawnChia @~Walker Yapi @Leung KH๐Ÿ€ please take note and plan accordingly. Cast plan on 13/05/2023.
 +60 16-837 8881: ๐Ÿ‘Œ๐Ÿป
 Leung KH๐Ÿ€: Noted


Azman HKL: Mitsubishi on site to check office & hotel lift pit wall at basement to ground floor.


+60 10-941 8970: Bottom bar gl J-K/8-11 in progress
 +60 10-941 8970: And beam reinforcement bar gl J-L/5-8 99% progress