SITE GROUP
Kadapi J. PROMES: Bin center ground floor.
Kadapi J. PROMES: Susun bata sudah.
Azman HKL: Site picture progress.
10/05/2023.
6th floor
Azman HKL: 2nd floor. Zone 5. Slab rebar & M&E in progress.
Azman HKL: M&E runs conduit on slab.
Azman HKL: 2nd floor, zone 4. Beam rebar in progress.
Azman HKL: Basement. Zone 5a. Retaining wall formwork in progress. Ground floor beam support scaffolding in progress.
Azman HKL: 1st floor. TB1. Support scaffolding for 2nd floor beam in progress
Azman HKL: Basement. 7B. Column rebar in progress.
Azman HKL: Ground floor. TA1. Slab formwork & lift formwork in progress.
NSC GROUP
Azman HKL: Basement..staircase 7 brick layer
Azman HKL: Basement..staircase 8..plaster base
Azman HKL: Basement..concrete stiffener brick wall
+60 12-843 3877: Breickwall baru mula Bos
Mungking 2 minggu lagi baru mau tambah men power
No comments:
Post a Comment