Monday, May 8, 2023

09 MAY 23 HKL

SITE GROUP


Azman HKL: Site progress.
8/05/2023.
Bird view.
 Azman HKL: @~YoonYK request bsok untuk cek lift pit wall at Hotel & Office.
 +60 19-821 8251: Sekarang saya on the way haha
 Azman HKL: Alamak.. sekarang masih belum siap tu..😅minta bsok la.
 Azman HKL: Boleh juga kalau cek saja.
+60 19-821 8251: Besok bah jika begitu. Haha
 Azman HKL: Bsok la.. 😅.


NSC GROUP

 Azman HKL: Site progress.
9/05/2023.
Bird view.
Azman HKL: 6th floor. All column cast.
 Azman HKL: 2nd floor. Zone 5. Slab & beam rebar in progress.
 Azman HKL: 2nd floor. Zone 4. Slab formwork and rebar in progress
Azman HKL: 1st floor. TB1 slab cast.
 Azman HKL: Basement zone 5a. Retaining wall in progress.
Azman HKL: 1st floor TA1 in progress. Lift pit rebar and formwork in progress.
 Azman HKL: Basement watertank. Top Plinth level and screed in progress

 Azman HKL: Today M&E coordination meeting after subcon weekly meeting. 3.00pm















 