Tuesday, April 18, 2023

19 APR 23 HKL

SITE GROUP
Azman HKL: Site progress. 19/04/2023.
6th floor.
Azman HKL: Basement. Zone 2B/b. Cast. Column rebar and lift pit rebar in progress.
 Azman HKL: Retaining wall. Pipe sleeve installed.
 Azman HKL: 1st floor. Zone 4. Column rebar and 2nd floor scaffolding for beam in progress.
Azman HKL: 2nd floor formwork and beam rebar in progress. Ramp3 slab rebar in progress.
Azman HKL: Basement. Zone 5a. Plinth formwork and lift formwork in progress. Conduit in lift formwork in progress.
 Azman HKL: Ground floor, zone 11. Column rebar and scaffolding support for 1st floor beam in progress.

NSC GROUP
Azman HKL: Done pipe sleeve inspection. @~Nasri can proceed to closure. TQ.
Azman HKL: Basement water tank. Brick layer in progress.
 Azman HKL: Ramp 3. Done inspection with consultant. ๐Ÿ‘ŒLighting point above void area and beam only. @Mr. Voo @~Nasri  please can proceed.
Azman HKL: Done inspection with M&E consultant. Conduit runs in lift pit wall. @~Nasri @Mr. Voo . Please proceed.

Lo. W. H (HKL-Site Engineer): @~DartWeirdo ๐Ÿ‡ฒ๐Ÿ‡พ ada kah bro?
+60 16-801 0751: Esok ya ๐Ÿ™๐Ÿฟ๐Ÿ™๐Ÿฟ
 Lo. W. H (HKL-Site Engineer): ok bro





















 