Azman HKL: @~Nasri itu wall water stop sd pasang,boleh pasang formwork ke?
Azman HKL: KH @Leung KH🍀 tolong atur ini hari. Maw tutup itu wall ni pagi.
Azman HKL: Hai.. morning. Today coordination meeting 3.00pm at site meeting room. TQ
+60 19-821 8251: Sorry not able to come, currently on leave.
Raymond Chong. Y. F (HKL P. Manager): get LIAW to attend
Azman HKL: 18/04/2023.
Site progress.
6th floor.
Azman HKL: Basement. Zone 2B/b. 1st cast done. 2nd cast by today.
Azman HKL: 1st floor. Zone 4. Column rebar in progress.
Azman HKL: 2nd floor slab. Form work in progress. Ramp 3. Slab rebar in progress
Azman HKL: Basement retaining wall. Installing pipe in progress thru wall in progress.
+60 19-821 8251: Liaw also on leave. I try to ask my colleague.
+60 19-821 8251: Kindly inform my colleague will arrived late a bit. Thanks.
Azman HKL: M&E coordination meeting 3pm after technical meeting. PIC please attend. TQ.
Azman HKL: After weekly subcon meeting.