Azman HKL: Good morning. 
Site progress. 12/04/23.
6th floor.
Azman HKL: 1st floor. Zone 4. Column rebar and closure  in progress.
Azman HKL: Ramp 3. Rebar in progress.
 Azman HKL: 1st floor, Lift wall in progress.
Azman HKL: Ground floor. Zone 11. Slab formwork in progress.
Azman HKL: Ramp 3. DCC runs conduit at rebar. 💪
Azman HKL: DCC check conduit before brick wall.
Kadapi J. PROMES: Dear NSC's, basement brick laying started. Please check ur installation either need opening through wall. U can came and do a marking on site. We appreciated your cooperation. Tq
Kadapi J. PROMES: Please lease with maincon and brick laying contractor for better cooperation.🙂.


NSC GROUP
+60 14-331 3232: @Edwin Chen 013 boss morning..tolong suru orang atur pinda barang kamu..sy mau set tu staircase suda..tq🙏🏻
Edwin Chen 013: Ready for us to move? The scaffolding frame already remove?
+60 14-331 3232: Sedang buka scaffolding..tolong suru orang boss turun atur laa..tq boss🙏🏻

Azman HKL: @~ShawnChia @~Leppong @~DartWeirdo 🇲🇾 @~Walker Yapi @Leung KH🍀 basement watertank area. Brick Wall run in progress. Any openings at the wall please inform on site.
+60 16-837 8881: Noted

 Edwin Chen 013: We have CW and waste pipe in this wall. All will be underneath the beam


















 