Azman HKL: Good morning.
28/03/2023. Site progress.
Zone 2D/b. 1st floor. Slab top rebar in progress.
Azman HKL: DCC on site runs conduit at slab rebar.
Azman HKL: 1st floor column rebar in progress
Azman HKL: Zone 1&2. 1st floor. Slab formwork and clearing in progress.
Azman HKL: Zone 2D/b. Scaffolding for 2nd floor work in progress.
Azman HKL: 6th floor. Column rebar in progress.
Azman HKL: Zone 2&3. Basement foundation. Rebar and cable post tensioning in progress.
Azman HKL: DCC at 6th floor, runs conduit box at column rebar.👆
Azman HKL: F/9
Azman HKL: I/9
Azman HKL: Column I/10.
NSC GROUP
Azman HKL: King Hong & econmech on site to install M&E item.
Azman HKL: M&E Coordination Meeting no15.