Azman HKL: Good morning.
Site progress. 14/03/23. Zone 1&2. Ground floor. Ramp2. Rebar n housekeeping in progress.
Azman HKL: Zone 2&3. Foundation rebar in progress. Earthing services in progress.
Azman HKL: Zone 1D/b. 1st floor slab and beam formwork in progress.
Azman HKL: 6th floor column rebar.
Azman HKL: GL: E-F/7-9. Basement foundation lean con casted. Foundation rebar in progress.