Sunday, March 12, 2023

13 MAR 23 HKL

SITE GROUP

Azman HKL: Good morning. 
13/03/23. Site progress. Zone 1&2. Ramp 3 area rebar in progress. Electrical conduit in progress.
Azman HKL: Ramp 2. Conduit installation in progress.
Azman HKL: Zone 1D/a. 1st floor rebar.
Azman HKL: 6th floor. Column work.
Azman HKL: Zone 1D/b. Ground floor column in progress.

 Azman HKL: Zone 2&3. Basement foundation done lean con.
 Azman HKL: GL: E-F/6-9 earthwork in progress














 

No comments:

Post a Comment

EGMALL NSC (23 SEPT 2024)

  EGMALL NSC (23 SEPT 2024) [23/9/2024 9:24 AM] EG MALL Mr Lo: @HIDAYA KH office Num ft ya Sini thanks [23/9/2024 9:24 AM] EG MALL Mr Lo: ...