Azman HKL: Good morning.
13/03/23. Site progress. Zone 1&2. Ramp 3 area rebar in progress. Electrical conduit in progress.
Azman HKL: Ramp 2. Conduit installation in progress.
Azman HKL: Zone 1D/a. 1st floor rebar.
Azman HKL: 6th floor. Column work.
Azman HKL: Zone 1D/b. Ground floor column in progress.
Azman HKL: Zone 2&3. Basement foundation done lean con.
Azman HKL: GL: E-F/6-9 earthwork in progress