Friday, March 10, 2023

11 MAR 23 HKL

 NSC GROUP

Azman HKL: Sorry. Will be late. Still at Tebobon traffic.


Azman HKL: Good morning.
Site progress.11/03/23
6th floor.
Azman HKL: Zone 1&2. Ground floor, formwork & rebar for Ramp 2 in progress. 1st floor slab formwork in progress. Column rebar in progress.
Azman HKL: Zone 1D/a. 1st floor slab rebar. Ramp 5 formwork and rebar in progress.
 Azman HKL: Zone 2&3. Foundation rebar in progress. Earthwork in progress.