Thursday, March 9, 2023

10 MAR 23 HKL

 NSC GROUP



[Azman HKL: Good morning.
Site progress. 10/03/23.
6th floor. Column..
Azman HKL: 1st floor slab.
Azman HKL: Zone 1D/b. Basement column in progress.
Azman HKL: Zone 1&2. 1st floor. Ramp 2 formwork in progress. 1st floor slab in progress.
 Azman HKL: Zone 2&3. slab foundation & Earthwork in progress.
Azman HKL: Test point inspection..
Lo. W. H (HKL-Site Engineer): the toilet TR3 will have drop at such to make way for the wc installaton and placement
Lo. W. H (HKL-Site Engineer): we will have block, drop line, separating SFL +11.90 toilet area and +11.95 outside of toilet area
Lo. W. H (HKL-Site Engineer): @Edwin Chen 013 @KH Karen @KH SU YEE CHONG @Leung KH🍀
Azman HKL: @DartWeirdo 🇲🇾 ini la tu. Check AHU plinth sana.👆🙏













No comments:

Post a Comment

EGMALL COORDINATION (26/6/2025)

   EGMALL COORDINATION (26/6/2025) [26/6/2025 4:41 PM] Azman HKL: Consultant commented. DCC ada orang maw rectify ini ASAP. 👏 [26/6/2025 4:...