Azman HKL: Good morning.
Site progress. 9/03/23.
6th floor.
Column rebar in progress.
Azman HKL: Zone 1D/a. 1st floor. Slab rebar and M&E services in progress.
Azman HKL: Zone 1D/b. Ground floor. Column rebar in progress.
Azman HKL: Column rebar in progress. Ground floor.
Azman HKL: Zone 1&2. Ground floor. 1. Ramp 2 formwork in progress. 2. 1st floor beam formwork in progress. 3. Column rebar in progress.
Azman HKL: Latest 6th floor column. Tonite subcon OT to install column rebar.
Kadapi J. HKL: Jangan lupa point pada column bossku.
Azman HKL: @Leppong @. F/9, I/9, I/10 👆
] +60 17-866 0355: Ok