Azman HKL: Good morning.
Today site progress. 8/3/23.
Zone 1D/b. Ground floor slab casted.
Azman HKL: Zone 1D/a. 1st floor. Slab rebar inprogress.
Azman HKL: Zone 2&3. Basement foundation rebar in progress
Azman HKL: Zone 1&2. Ground floor. Column rebar in progress..
Azman HKL: Basement foundation. GL: E-F/7-9 earthwork in progress.
Azman HKL: 6th floor. Column in progress.
Azman HKL: Ramp 2. Slab formwork in progress.
Kadapi J. HKL: Jgn lupa point kita d tiang bossku