NSC GROUP
Azman HKL: Good Morning.
22/02/2023. Site progress.
6th floor. Zone 2. Slab rebar in progress.
Azman HKL: 6th floor. Slab bottom rebar in progress.
Azman HKL: Basement. Zone 1D. Ground floor beam scaffolding formwork in progress.
Azman HKL: 1st floor slab formwork in progress.
Azman HKL: Beam support at basement zone 1D in progress.
Azman HKL: Ground floor. Zone 1&2. Column rebar in progress.
KH SU YEE CHONG: @Azman HKL as per our discussion, tomorrow morning 9am we need your kind assist of mobile crane and tower crane to move our tank materials to basement near tank area.. thanks🙏
Azman HKL: Ok. Make Sure your man on site early before 9am. 👌
KH SU YEE CHONG: change to 10am ya, ok?
Azman HKL: Ok..
KH SU YEE CHONG: thanks
No comments:
Post a Comment