Tuesday, February 21, 2023

21 FEB 23 HKL

SITE GROUP

Azman HKL: Good morning.
21/02/2023. Site progress. 6th floor. Zone 2. Slab beam rebar in progress.
Azman HKL: 6th floor. Slab beam rebar in progress.
Azman HKL: 1st floor basement slab from work in progress.
Azman HKL: Basement. Zone 1D. Retaining wall casted.
Azman HKL: Basement. Zone 2&3. Earthwork in progress.
 Azman HKL: FRP water tank delivery on site.












 