Azman HKL: Good morning. 6/2/2023.
Site progress.
Basement, zone 1D. Slab rebar in progress
Azman HKL: Ground floor. Zone 1A & 1B. Slab rebar in progress.
Azman HKL: Ground floor. M&E services in progress.
Azman HKL: Plumbing pipe sleeve installed.
Azman HKL: SPD opening installed.
Azman HKL: Ground floor. GL: J/5, J/6, K/5& K/6 column rebar in progress.
NSC GROUP
Lo. W. H (HKL-Site Engineer): DCC, the softcopy og your shop drawing should come togethr with the submission ..this is requested by Chris, EG for their awareness, if anything \.
Lo. W. H (HKL-Site Engineer): *of
[+60 19-895 9900: Ok, will do
Lo. W. H (HKL-Site Engineer): your letter bear the ref: ES-21
Lo. W. H (HKL-Site Engineer): i will hold the submission until you issue us the softcopy