Friday, January 13, 2023

14 JAN 23 HKL

SITE GROUP
 Azman HKL: Morning. Site progress. 
14/01/2023. 5th floor
Azman HKL: Basement zone 2. Column & earthwork in progress
 Azman HKL: Basement. Zone 1D. Wall rebar and formwork in progress. Column in progress.
Azman HKL: Ground floor beam & slab formwork in progress.
 Azman HKL: For info. 
This basement zone 1D wall casting plan is on 17/01/2023. Tuesday. Inspection is on 16/01/2023, Monday. Please make sure all services are ready before wall formwork closure.


NSC GROUP


Azman HKL: Installing pipe sleeve thru wall in progress.