SITE GROUP
Azman HKL: Morning. Site progress.
14/01/2023. 5th floor
Azman HKL: Basement zone 2. Column & earthwork in progress
Azman HKL: Basement. Zone 1D. Wall rebar and formwork in progress. Column in progress.
Azman HKL: Ground floor beam & slab formwork in progress.
Azman HKL: For info.
This basement zone 1D wall casting plan is on 17/01/2023. Tuesday. Inspection is on 16/01/2023, Monday. Please make sure all services are ready before wall formwork closure.