Thursday, January 12, 2023

13 JAN 23 HKL

NSC GROUP

Azman HKL: Good morning. 
Site progress. 13/01/2023
5th floor..
Azman HKL: 5th floor
Azman HKL: Basement zone 2. 1. Wall rebar and formwork closing in progress. 2. Column work in progress. 3. Earthwork in progress.
Azman HKL: Basement. Wall rebar in progress. GL: L/4a-7.
Azman HKL: Basement. Zone 1D. Column, lift pit, wall formwork and rebar in progress..
 Azman HKL: Lift pit form work.
Azman HKL: Ground floor sanitary pipe in progress.
Azman HKL: TC 2 foundation rebar.