Tuesday, January 31, 2023
01 FEB 23 HKL
Azman HKL: Good morning.
1/2/2023. Site progress.
5th floor. Slab formwork in progress.
Azman HKL: 5th floor column. Casted.
Azman HKL: Ground floor. Slab rebar and M&E services installation in progress.
Azman HKL: Ground floor. Formwork in progress.
Azman HKL: Basement. Foundation casted.
Azman HKL: Basement pile cap foundation.
Azman HKL: Ground floor conduit installation
Azman HKL: Ground floor slab. M&E services target done 11am. Bossku @Kadapi J. HKL can comeand ready for joint inspection at 1.30pm.
+60 12-833 6147: 👍🏻
Azman HKL: Heavy rain on site.
Monday, January 30, 2023
31 JAN 23 HKL
Azman HKL: Good morning.
31/01/2023. Site progress. Zone 1S. Ground floor slab. Rebar & M&E services in progress.
Azman HKL: Basement. Zone 2A/a. Foundation casted
Azman HKL: Basement zone 1D. Earthwork in progress.
Azman HKL: 6th floor. Slab formwork in progress
Azman HKL: Basement zone 1 & 2. Slab formwork in progress.
Azman HKL: Lift pit opening inspection at ground floor Mall slab with Mitsubishi and consultant.
Sunday, January 29, 2023
Subscribe to:
Comments (Atom)
-
EG MALL NSC ( 11 MARCH 2025) [11/3/2025 10:26 AM] +60 16-837 8881: Belum habis naik bata tapi mahu paitong sudah ? 6th floor. Genset roo...
-
EGMALL COORDINATION (22/4/2025) 0198218251(1.42PM) : Petang Azman, tolong pasang pintu untuk motor room di office block dekat tingkat 21....